The project, valued at more than R37 million, was initiated in June 2022 to relieve the overcrowding at the school and provide 13 more classrooms.The construction was supposed to be completed in 2024. However, the completion date has been moved to 2025 due to construction being halted many times over a short period by “gun-wielding” people who claim to be from the construction forum.
Today, one group would come to demand the 30% payment and construction would continue, and later a different group would come with the same demands